Dear partners,
We would like to inform you that following the public consultations held in the period 5 August 2019 – 23 August 2019 with Decision under Protocol of Bulgartransgaz EAD Management Board No. 382/04.09.2019 the values of the parameters of Art. 25 of Daily Imbalance and Neutrality Charge Calculation Methodology (Methodology) valid for Gas Year 2019/2020 have been determined, namely:
- The small adjustment under Art.12(4) of the Methodology amounts to 8 %;
- The clearing period for the neutrality account for balancing shall be 6 months;
- The criteria for setting the price of the natural gas for balancing under 4 of Additional Provisions of the Methodology shall apply.