URGENT MARKET MESSAGE on temporary transmission capacity limitation

Message ID:

 UMM-GTNTT-005

Time and Date of UMM publishing::

 30.05.2014, 08:00 CET

Message type and history of prior publications regarding the same event:

  New message .

Balancing zone:

Gas transmission network for transit transmission

Affected Point:

IP Strandja/Malkoclar - exit

Asset type affected:

Compressor station

Asset unit affected:

Compressor station Losenets

Starting time of capacity change:

 02.06.2014, 08:00 CET

Estimated time at which the assets concerned will be partly/or wholly available again:

 01.07.2014, 08:00 CET

Estimated duration of unavailability or uncertainty:

29 days

Cause:

Scheduled survey of the technical state of the entry and exit gas gatherings

Technical capacity (of the asset concerned during normal situation), (kWh per gas day):

 470 202 500 kWh /d

Flow capacity influenced (kWh per gas day):

                                                                     178 442 500 kWh /d

Available capacity of the asset concerned  during the outage, (kWh per gas day):

291 760 000 kWh /d

Additional information: