URGENT MARKET MESSAGE on temporary transmission capacity limitation

Message ID:

 UMM-NGTN-009

Time and Date of UMM publishing:

 05.08.2014, 08:00 CET

Message type and history of prior publications regarding the same event:

New message

Balancing zone

National gas transmission network

Affected Point

GRS Sofia 2. GRS Sofia 3, GRS Sofia 4, AGRS Chepintsi, AGRS Novi Iskar, GRS Pernik  – exit points

Asset type affected

Gas pipeline

Asset unit affected :

Gas pipeline branch

Starting time of capacity change :

16.08.2014, 05:00 CET

Estimated time at which the assets concerned will be partly/or wholly available again:

17.08.2014, 17:00 CET 

Estimated duration of unavailability or uncertainty :

 36 hours

Cause :

Scheduled gas pipeline branch from LV Gorno Bogrov to PF Novi Iskar  repair

Technical capacity (of the asset concerned during normal situation), (kWh per gas day):

 47 030 670  kWh /d

Flow capacity influenced , (kWh per gas day):

 47 030 670 kWh /d

Available capacity of the asset concerned  during the outage, (kWh per gas day):

  0  kWh /d

Additional information :