URGENT MARKET MESSAGE on temporary transmission capacity limitation

Message ID:

 UMM/GTNTT-013

Time and Date of UMM publishing::

13.08.2015, 12:00 CET

Message type and history of prior publications regarding the same event:

 New message

Balancing zone:

Gas transmission network for transit transmission

Affected Point:

AGRS Kyustendil - exit

Asset type affected:

Gas pipeline

Asset unit affected:

Gas pipeline

Starting time of capacity change:

29.08.2015, 07:00 CET

Estimated time at which the assets concerned will be partly/or wholly available again:

31.08.2015, 07:00 CET

Estimated duration of unavailability or uncertainty:

48 hours

Cause:

Planned gas pipeline repair

Technical capacity (of the asset concerned during normal situation), (kWh per gas day):

413 942 kWh /d

Flow capacity influenced (kWh per gas day):

413 942 kWh /d

Available capacity of the asset concerned  during the outage, (kWh per gas day):

        0 kWh /d

Additional information: